Good News|FRES JiFu 6 WELL LNG Project Successfully Achieved Liquid Production
- News and Insights
- 2023-12-27
(Summary description)
Good News|FRES JiFu 6 WELL LNG Project Successfully Achieved Liquid Production
(Summary description)
- Time of issue:2023-12-27
On December 24th, the 100,000 m³/day LNG project of Well JiFu 6 was successfully commissioned and put into production of liquefied natural gas, marking a successful year for 2023.
The project started civil construction on November 15, 2023, and the machinery was completed on December 10. Well opening and commissioning was carried out on December 20, and liquid production was put into operation on December 24. It only took 40 days to set a new record for the construction of similar projects. The hard work and unremitting efforts of the project team and all colleagues involved in the construction are greatly appreciated.
The JiFu 6 Well 100,000 m3/day LNG station is carried out by FRES, which is responsible for the transition installation and operation project of LNG skid-mounted equipment. The successful commissioning of this project provides a good example for the sustainable development of the company's scattered gas recovery and processing services, and has accumulated valuable experience for the construction and operation of similar projects in the future.