Heshen IV Project
200,000 Nm³/d production
Heshen IV Project
- Case Studies
- 2021-06-01
(Summary description)200,000 Nm³/d production
Heshen IV Project
(Summary description)200,000 Nm³/d production
- Time of issue:2021-06-01
Chief:
Sun Zhiguo - Responsible for operations management
On 10th March 2021, the 200,000Nm³/d LNG Liquefaction Skid Equipment in Sichuan, also known as the Heshen IV Project, was successfully put into operation. Supplied by parent company Furuise and constructed by Furui Energy, the project also completed successful liquefaction.
The challenge
Completing a large-scale whole industry chain project in just 130 days
Timeline of project works
- Design: on 8th October 2020, project design commenced
- Manufacturing: on 5th December 2020, the first batch of goods was shipped
- Installation: on 31st January 2021, the mechanical construction was completed
- Commissioning: on 10th March 2021, the project underwent successful testing, and was subsequently put into official operation
The solution
Prompt yet thorough design, manufacturing, installation, and commissioning processes enabled the project to perform effectively and continue to surpass the performance of similar projects both domestically and internationally.
Efficient project management was vital to the success of Heshen IV Project, and required effective collaboration between the design, manufacturing, and construction teams.